OTHER PROJECTS OPERATED
 

TAMPICO SOLAR SOLAR FARM

 

Tampico Solar, S.A. de C.V.
PRIANA POWER
Development construction of a solar park of 36 MW of power. A total of 350 containers imported. Located in Guanajuato. Estatus under construction, year of execution 2019.

  ---------------------------------------------------------------------------------------------
 

POLLUX GALENA SOLAR FARM

 

Reden Services México, S.A. de C.V.
GRUPO ALTIUS
Development construction of a solar park of 91 MW of power. A total of 500 containers imported. located in Galeana, Nuevo León. Status under construction, year of execution 2019.

  ---------------------------------------------------------------------------------------------
 

LA LUCHA SOLAR FARM

 

Grupo Ortiz Energía México, S.A. de C.V.
RAMINATRANS
Development construction of a solar park of 163 MW of power. A total of 1,400 containers imported. Located in Torreón, Coahuila. Status under construction, year of execution 2019 and 2020.

  ---------------------------------------------------------------------------------------------
 

EL CARMEN

 

Iberdrola Energía Escobedo, S.A. de C.V.
IBERDROLA
Combined cycle power plant with two gas turbines and two steam turbines with 866 MW of power located in Escobedo, Monterrey. Status under construction, year of execution 2018.

  ---------------------------------------------------------------------------------------------
 

TOPOLOBAMPO III

 

Iberdrola Energía Topolobampo, S.A. de C.V.
IBERDROLA
Combined cycle power plant with two gas turbines and two steam turbines with 681 MW of power. Located in Ahome, Sinaloa. Status under construction, year of execution 2018.

  ---------------------------------------------------------------------------------------------
 

FV OREJANA SOLAR POWER PLANT

 

Fisterra Energy Orejana, S. de R.L. de C.V.
AVANZIA - MAETEL
Development construction of a solar park of 126 MW of power. A total of 775 containers imported. Located in Rancho la Orejana, Hermosillo, Sonora. Status under construction, year of execution 2018.

  ---------------------------------------------------------------------------------------------
 

FV SANTA MARÍA SOLAR POWER PLANT

 

Fisterra Energy Santa María, S.A.P.I. de C.V.
AVANZIA - MAETEL
Development construction of a solar park of 166 MW of power. A total of 854 containers imported. Located in Santa María, Chihuahua, Chihuahua. Status under construction, year of execution 2018.

  ---------------------------------------------------------------------------------------------
 

XOXOCOTLA SOLAR POWER PLANT

 

Avanzia Energía, S.A. de C.V.
AVANZIA
Development construction of a 70 MW solar park. A total of 500 containers imported. Located in Cuernavaca, Morelos. Status under construction, year of execution 2018.

  ---------------------------------------------------------------------------------------------
 

MEX SOLAR I SOLAR POWER PLANT

 

Avanzia Energía, S.A. de C.V.
AVANZIA - MAETEL
Development construction of a solar park of 30 MW of power. A total of 250 containers imported. Located in Allende, Guanajuato. Status under construction, year of execution 2018.

  ---------------------------------------------------------------------------------------------
 

MEX SOLAR II SOLAR POWER PLANT

 

Avanzia Energía, S.A. de C.V.
AVANZIA - MAETEL
Development construction of a solar park of 43 MW of power. A total of 250 containers imported. Located in Allende, Guanajuato. Status under construction, year of execution 2018.

  ---------------------------------------------------------------------------------------------
 

38 CC NORTE III

 

Techint, S.A. de C.V.
TECHINT
Combined cycle power plant consisting of two power islands with gas and steam turbines with a power of 928 MW with TOSHIBA/HITACHI technology. Located in Chihuahua. Status under construction, year of execution 2018.

  ---------------------------------------------------------------------------------------------
 

ESCOBEDO NOROESTE

 

Iberdrola Energía Escobedo, S.A. de C.V.
IBERDROLA
Combined Cycle Power Plant with two gas turbines and two steam turbines, with 850 MW of power, with TOSHIBA technology, located in Escobedo, Monterrey. Status under construction, year of execution 2017.

  ---------------------------------------------------------------------------------------------
 

SANTIAGO SOLAR FARM

 

Iberdrola Renovables Centro, S.A. de C.V.
IBERDROLA
Solar park located in the Santiago municipality. Solar panels imported with a capacity of 170 MW. The total number of containers to be imported is 1,000 units by the Manzanillo customs office. Status under construction, year of execution 2017.

  ---------------------------------------------------------------------------------------------
 

DIESEL CADEREYTA REMODELING PROJECT

 

Remodelación Diesel Cadereyta, S.A. de C.V.
AVANZIA
Remodeling of the refinery Ing. Héctor R. Lara Sosa. His first stage consists in the importation of a reactor and the catalysts. Located in Monterrey. Status operating, year of execution 2017.

  ---------------------------------------------------------------------------------------------
 

ALFA COGENERACIÓN ALTAMIRA

 

Alfa Cogeneración Altamira, S.A. de C.V.
AVANZIA
Combined cycle cogeneration plant with two gas turbines and two steam turbines for condensing extractors with 850 MW of power with SIEMENS technology. Located in Altamira, Tamaulipas. Status under construction, year of execution 2017.

  ---------------------------------------------------------------------------------------------
 

KIEWIT ENERGY USA

 

KEM-GIA Constructora, S. de R.L. de C.V.
KIEWIT
Importation of equipment, materials and tools for the adaptation of a pipeline for gas for the final customer who is TRANSCANADA. Located in El Bajío, Querétaro. Status under construction, year of execution 2017.

  ---------------------------------------------------------------------------------------------
 

GRUPO PERC

 

Energéticos Fusión, S.A. de C.V.
FUSION
Importation of pipes and tank-cars with diesel through border customs to El Bajío. On average 40 pipes and 15 tank-cars per month. Operating status, year of execution 2017 and 2018.

  ---------------------------------------------------------------------------------------------
 

ENESTAS ENERGY AND GAS

 

Enestas Energy and Gas, S.A. de C.V.
ENESTAS
Importation of pipes with cryogenic natural gas through border customs to Jalisco, Guadalajara, for greenhouses. On average 40 pipes per month. Operating status, year of execution 2017, 2018 and 2019.

  ---------------------------------------------------------------------------------------------
 

CC COGENERACIÓN SALAMANCA PROJECT

 

Iberdrola Energía y Construcción México, S.A. de C.V.
IBERDROLA
Import of equipment for 430 MW of power electric power plant with GE technology in Salamanca, Guanajuato. Status operating, year of execution 2016.

  ---------------------------------------------------------------------------------------------
 

QUINTA UNIDAD

 

Iberdrola Energía Monterrey, S.A. de C.V.
IBERDROLA
Extension of the Fifth Unit of the combined cycle plant in the Dulces Nombres Complex with 1,121 MW of power with ALSTOM technology. Located in the Municipality of Pesquería, Monterrey. Operating status, year of execution 2016.

  ---------------------------------------------------------------------------------------------
 

BAJÍO COGENERACIÓN

 

Iberdrola Cogeneración Bajío, S.A. de C.V.
IBERDROLA
Cogeneration Plant, for steam and electricity production to cover the needs of Kimberly Clark, with 54 MW of power, with TOSHIBA technology, located in Bajío, Querétaro. Status under construction, year of execution 2016.

  ---------------------------------------------------------------------------------------------
 

NUEVO PEMEX COMPLEX GAS PROCESSOR

 

Avanzia Instalaciones, S.A. de C.V.
AVANZIA
Construction and commissioning of the conditioning of the condensate sweetener and stabilizer plants no. 2, 3 and 4. Construction and commissioning of hydrocarbon fractionation plants no. 1 and 2. Located in Villahermosa, Tabasco. Status operating, year of execution 2016.

  ---------------------------------------------------------------------------------------------
 

PROYECTO TG7 MADERO PROJECT

 

ACS Servicios Comunicaciones y Energía México, S.A. de C.V.
AVANZIA
Gas turbogenerator and heat recovery at the "Francisco y Madero" Refinery, with 20 MW of power with GE technology. Located in Tamaulipas. Status under construction, year of execution 2016.

  ---------------------------------------------------------------------------------------------
 

DUBA PROJECT

 

Avanzia Instalaciones, S.A. de C.V.
AVANZIA
Ultralow sulfur diesel, new diesel hydrosulfator plant. Located in Veracruz. Status under construction, year of execution 2016.

  ---------------------------------------------------------------------------------------------
 

AGRONITROGENADOS PROJECT

 

Avanzia Instalaciones, S.A. de C.V.
AVANZIA
Rehabilitation of the agronitrogenados plant with GE technology in Coatzacoalcos, Veracruz. Status under construction, year of execution 2016.

  ---------------------------------------------------------------------------------------------
 

VALLE DE MÉXICO II

 

Valle de México II, S.A. de C.V.
AVANZIA
Combined cycle power plant with two gas turbines and two steam turbines with 750 MW of power with SIEMENS technology. Located in Acolman, Estado de México. Status under construction, year of execution 2016.

  ---------------------------------------------------------------------------------------------
 

CCC MORELOS 264 PROJECT

 

CC 264 Centro Morelos, S.A. de C.V.
ABENGOA
Import of all the necessary equipment for the construction of the combined cycle power plant named 264 CC Centro. 4 power-capacity islands with a power of 642.33 MW with GE technology. Located in the city of Cuautla, Morelos. Status operating, year of execution 2016.

  ---------------------------------------------------------------------------------------------
 

ENERGÍA VALLE DE MÉXICO I

 

EVM Energía Valle de México, S.A.P.I. de C.V.
TSK
Development of 3 power islands derived aero turbines with a power of 94 MW with GE technology. Located in Acolman, Estado de México. Operating status, year of execution 2016.

  ---------------------------------------------------------------------------------------------
 

PIER II QUECHOLAC

 

Pier II Quecholac Felipe Ángeles, S.A. de C.V.
IBERDROLA
66 MW wind power production project with 33 GAMESA wind turbines technology. Located in the State of Puebla. Operating status, year of execution 2015.

  ---------------------------------------------------------------------------------------------
 

COGENERACIÓN RAMOS PROJECT

 

Iberdrola Cogeneración Ramos, S.A. de C.V.
IBERDROLA
Supply of two power islands: recovery boiler gas and steam turbogenerator system with 52 MW of power with GE technology in Coahuila. Status operating, year of execution 2015.

  ---------------------------------------------------------------------------------------------
 

35 CC BAJA CALIFORNIA III

 

Iberdrola Energía Baja California, S.A. de C.V.
IBERDROLA
Power island supply: recovery boiler gas and steam turbogenerator system with 300 MW of power with GE technology. Located in the “Jovita” Baja California. Operating status, year of execution 2015.

  ---------------------------------------------------------------------------------------------
 

BAJA CALIFORNIA SUR IV PROJECT

 

Abener Energía, S.A. de C.V.
ABENGOA
Importation of all the necessary equipment for the construction of the internal combustion plant through a diesel engine plus generator with a power of 43 MW with ALSTOM technology. Located in Baja California Sur. Status operating, year of execution 2015.

  ---------------------------------------------------------------------------------------------
 

ACC 4T

 

ACC 4T, S.A. de C.V.
ABENGOA
Extension of the Nuevo Pemex Project with a fourth train. Located in Villahermosa, Tabasco. Status to begin, year of execution 2015.

  ---------------------------------------------------------------------------------------------
 

DOMINICA II CENTRAL

 

Energía Nueva Energía Limpia México, S. de R.L. de C.V.
GAMESA
Importation of a 50 wind turbines with a total production of 100 MW. Located in Las Charcas, San Luis Potosí. Operating status, year of execution 2015.

  ---------------------------------------------------------------------------------------------
 

PEMEX DRIVEN RACK PIPELINES

 

Iberdrola Energía y Construcción México, S.A. de C.V.
IBERDROLA
Import of steel pipe for conduction in the PEMEX refinery in Salamanca, Guanajuato with GE technology. Operating status, year of execution 2014.

  ---------------------------------------------------------------------------------------------
 

ABENT 3T

 

Abent 3T, S. de R.L. de C.V.
ABENGOA
The Nuevo Pemex Cogeneration plant is expanded with a new Combined Cycle train (Gas Turbogenerator System plus Steam Turbogenerator System) with a power of 250 MW with ALSTOM/GE technology. Located in Villahermosa, Tabasco. Status under construction, year of execution 2014.

  ---------------------------------------------------------------------------------------------
 

BIÍ HIOXIO NORTE WIND POWER PLANT

 

Gesa Eólica México, S.A. de C.V.
GAMESA
Importation of a 23 wind turbines with a total production of 46 MW. Located in Juchitán de Zaragoza, Oaxaca. Operating status, year of execution 2014.

  ---------------------------------------------------------------------------------------------
 

BIÍ HIOXIO SUR WIND POWER PLANT

 

Gesa Eólica México, S.A. de C.V.
GAMESA
Importation of a 57 wind turbines with a total production of 114 MW. Located in Juchitán de Zaragoza, Oaxaca. Operating status, year of execution 2014.

  ---------------------------------------------------------------------------------------------
 

AROLITOS WIND POWER PLANT

 

Eólica Dos Arbolitos, S.A.P.I. de C.V.
GAMESA
Importation of a 37 wind turbines with a total production of 74 MW. Currently under construction. Located in the Dos Arbolitos Zone, Juchitán de Zaragoza, Oaxaca. Status operating, year of execution 2014.

  ---------------------------------------------------------------------------------------------
 

DOMINICA I WIND POWER PLANT

 

Energía Nueva Energía Limpia México, S. de R.L. de C.V.
GAMESA
Importation of a 50 wind turbines with a total production of 100 MW. Located in Las Charcas, San Luis Potosí. Operating status, year of execution 2014.

  ---------------------------------------------------------------------------------------------
 

SOLANA

 

Abengoa T & D
ABENGOA
Thermosolar plant with parabolic trough cylinder technology with 280 MW power with storage. Located in Gila Bend, Arizona. This project was born from the contract that Abengoa Solar signed with the Arizona Public Service (APS), the largest electricity company in Arizona. A total of 1,500 containers were imported through different customs. Status operating, year of execution 2013.

  ---------------------------------------------------------------------------------------------
 

"PIEDRA LARGA II" WIND POWER PLANT

 

Gamesa Eólica de México, S.A. de C.V.
GAMESA
Wind power project starting with 138 MW of production with 69 G80 wind turbines (10 already imported and 59 for 2014). Located in Unión Hidalgo, Oaxaca. Operating status, year of execution 2013.

  ---------------------------------------------------------------------------------------------
 

"SANTO DOMINGO" WIND POWER PLANT

 

Gesa Eólica México, S.A. de C.V.
GAMESA
Importation of 80 wind turbines that will form the Santo Domingo Wind Farm with a total production of 160 MW. It is located in Santo Domingo Ingenio, Oaxaca. Operating status, year of execution 2013.

  ---------------------------------------------------------------------------------------------
 

EL RETIRO WIND POWER PLANT

 

Eólica El Retiro, S.A.P.I. de C.V.
GAMESA
Importation of 37 wind turbines with a total production of 74 MW located in the Dos Arbolitos zone, Juchitán de Zaragoza, Oaxaca. Operating status, year of execution 2013.

  ---------------------------------------------------------------------------------------------
 

BIÍ HIOXIO WIND POWER PLANT

 

Gesa Eólica México, S.A. de C.V.
GAMESA
It consists of a 117 wind turbines that form the Bií Hioxio Wind Farm with a total production of 234 MW. It has 37 kits and is located in Juchitán de Zaragoza, Oaxaca. Operating status, year of execution 2013.

  ---------------------------------------------------------------------------------------------
 

OAXACA I WIND POWER PLANT

 

Recursos Eólicos de México, S.A. de C.V.
AVANZIA
We participate in the importation of asparagus and mortar for foundation. Status operating, year of execution 2012.

  ---------------------------------------------------------------------------------------------
 

"ZOPILOAPAN" WIND POWER PLANT

 

Eólica Zopiloapan, S.A. de C.V.
GAMESA
GAMESA equipment. 70 MW wind power project with 35 G80 wind turbines. Located in the town of Zopiloapan, Oaxaca. Operating status, year of execution 2012.

  ---------------------------------------------------------------------------------------------
 

BIÍ STIINU WIND POWER PLANT

 

Gesa Eólica México, S.A. de C.V.
GAMESA
Turnkey project for Eoliatec del Istmo S.A.P.I de C.V. It consists of 82 G80 generators of 2 MW each with a total production of 164 MW. Central located in the municipalities of Juchitán de Zaragoza, El Espinal, Asunción Ixtaltepec and Cuidad Ixtepec belonging to the Southwest of Oaxaca in the Region of El Istmo de Tehuantepec. Operating status, year of execution 2012.

  ---------------------------------------------------------------------------------------------
 

CCC NUEVO PEMEX

 

Abengoa Cogeneración Tabasco, S. de R.L. de C.V.
ABENGOA
Installation of a cogeneration plant with gas turbines and heat recovery which uses water and natural gas to produce steam and electricity with a power of 300 MW and 800 Ton /hr of steam with GE technology. Investment 461 million dollars. Located in Villahermosa, Tabasco. Operating status, year of execution 2011.

  ---------------------------------------------------------------------------------------------
 

"STIPA NAAYA" WIND POWER PLANT

 

Stipa Naaya, S.A. de C.V.
GAMESA
Wind farm named "Stipa Nayaa" in self-supply modality of 74 MW of 37 wind turbines of 2 MW each on an area of 514,283 hectares of a total of 33 landlords in the municipality of El Espinal, Oaxaca. Status operating, year of execution 2011.

  ---------------------------------------------------------------------------------------------
 

CENTRAL EÓLICA "PIEDRA LARGA" WIND POWER PLANT

 

Gamesa Eólica de México, S.A. de C.V.
GAMESA
Wind power project starting with 90 MW of production with 45 G80 wind turbines. Located in Unión Hidalgo, Oaxaca, which will allow to supply the electrical consumption of 65 facilities in Mexico (production plants and other operation centers) of Bimbo company. Investment 200 million dollars. Operating status, year of execution 2011.

  ---------------------------------------------------------------------------------------------
 

LA VENTA III

 

Energías Renovables La Venta III, S.A. de C.V.
IBERDROLA
Wind power project of 103 MW of production with 121 GAMESA wind turbines technology. Located in the Municipality of Santo Domingo, Oaxaca. Operating status, year of execution 2010.

  ---------------------------------------------------------------------------------------------
 

ENERTEK EXTENSION

 

Enertek, S.A. de C.V.
IBERDROLA
Import of a cogeneration plant for power expansion and 170 ton/hr of steam with a capacity of 110 MW with SIEMENS technology. Located in Altamira, Tamaulipas. Status operating, year of execution 2010.

  ---------------------------------------------------------------------------------------------
 

CCR LA CANGREJERA

 

CCR Platforming La Cangrejera, S.A. de C.V.
AVANZIA
Construction of the first phase of the aromatic project, of a catalytic reforming plant, at the CPQ La Cangrejera. Value of the project, three thousand 265 million 491 thousand 643 pesos. Location La Cangrejera, Coatzacoalcos, Veracruz. Operating. Status, year of execution 2010.

  ---------------------------------------------------------------------------------------------
 

AGUAPRIETA II THERMOSOLAR PLANT

 

Teyma, Gestión de Contratos de Construcción e Ingeniería, S.A.
ABENGOA
The Agua Prieta II thermosolar power plant is the first hybrid solar-gas power plant in Mexico. Located in the town of Agua Prieta, Sonora. The project consists of engineering, design and commissioning of the ISCC (Integrated Solar Combined Cycle) technology consisting of a 14 MW parabolic trough solar field with GE technology. A total of 1,200 containers were imported by different customs. Operating status, year of execution 2010.

  ---------------------------------------------------------------------------------------------
 

LA VENTOSA I

 

Parques Ecológicos de México, S.A. de C.V.
IBERDROLA
Construction of the first phase of a 20MW wind power plant with 10 wind turbines, GAMESA technology. In La Ventosa, Oaxaca. Status operating, year of execution 2009.

  ---------------------------------------------------------------------------------------------
 

LA VENTOSA II

 

Parques Ecológicos de México, S.A. de C.V.
IBERDROLA
Expansion of the Suction Cup I (La Ventosa I project) to reach 84 MW, with 30 wind turbines GAMESA technology. In La Ventosa, Oaxaca. Status operating, year of execution 2009.

  ---------------------------------------------------------------------------------------------
 

LA VENTA III

 

Parques Ecológicos de México, S.A. de C.V.
IBERDROLA
Wind power project of 103 MW of production, with 51 wind GAMESA turbines technology. Located in La Ventosa, Oaxaca. Operating status, year of execution 2009.

  ---------------------------------------------------------------------------------------------
 

167 CC SAN LORENZO

 

Dragados Proyectos Industriales México, S.A. de C.V. A. en P.
AVANZIA
Conversion of gas turbine to combined cycle of the central San Lorenzo to guarantee a net capacity of the steam cycle at 130 MW, through the integration of a steam turbogenerator, two steam generators per recovery, an air condenser and auxiliary systems. Located in Puebla. Operating status, year of execution 2008.

  ---------------------------------------------------------------------------------------------
 

TAMAZUNCHALE

 

Iberdrola Energía Tamanzuchale, S.A. de C.V.
IBERDROLA
Import of a combined cycle plant with 4 gas turbines and 2 steam turbines with GE technology with a capacity of 1,135MW. Located in San Luis Potosí. Status operating, year of execution 2007.

  ---------------------------------------------------------------------------------------------
 

29 CC NORTE

 

Fuerza y Energía de Norte de Durango, S.A. de C.V.
GAS NATURAL FENOSA
Construction of a combined cycle power plant with a gas turbine and a steam turbine with a capacity of 391.5 MW with SIEMENS technology. Located in Durango, operating. Status, year of execution 2007.

 

 
     

Derechos Reservados IEES 2007. Import and Export Energy Services es una division especializada de BSV Consultores de Comercio Internacional, S.C.